If you're planning a new kitchen in Cheadle Hulme, one of the first questions is always the same: how long will my house be in upheaval? The honest answer depends on the size of the room, whether you're changing the layout, and what's happening behind the walls, but there are realistic timelines you can plan around.
Most of the kitchens we fit in Cheadle Hulme fall into one of three categories, and the timescale changes quite a bit between them. A straightforward swap, where units go back in roughly the same positions as before, is the quickest option. A reconfigured kitchen with a new layout, new flooring and some plastering takes longer. A larger project involving structural work, such as knocking through to a dining room or adding an extension, takes the longest.
As a rough guide: a like-for-like refit in a typical Cheadle Hulme semi or terrace usually takes 1 to 2 weeks on site. A medium-sized kitchen with a new layout, replastering and new flooring is usually 3 to 4 weeks. A larger project with structural alterations, such as removing a wall between kitchen and dining room, can run to 5 to 8 weeks once you include the building work before the kitchen itself goes in.
On a medium-sized job, the first couple of days are strip out: removing the old units, disconnecting the cooker and dishwasher, and getting the room back to bare walls and floor. First fix plumbing and electrics follows, moving pipework and cabling to match the new layout, which in many Cheadle Hulme properties built in the 1930s or between the wars means working around older wiring and sometimes lead pipework that needs updating.
Plastering comes next and needs proper drying time, usually 3 to 5 days before it's ready for painting or tiling. Flooring goes down after that, then the units are built and fitted. This is where worktop choice matters for your timeline: if you're having a solid surface like quartz or granite, it has to be templated once the cabinets are in place, then cut off site, which typically adds 10 to 14 days before it can be installed. Laminate or wood worktops can usually be fitted the same week, so if you're on a tight deadline, that's worth discussing early with whoever is designing your kitchen.
The final stage covers appliance connection, splashback and tiling, decorating, and snagging, usually another few days once the worktop is in.
Several things commonly add time to a kitchen project in this area. Older Cheadle Hulme homes, particularly those near the village centre and around Gatley Road and Ravenoak Road, often have solid floors or chimney breasts that weren't expected to be part of the job until the walls are opened up. Finding this during strip out can add a few days while a plan is agreed.
Structural changes need building control sign-off, and if you're removing a load-bearing wall, a steel beam has to be sized by a structural engineer and ordered, which can take 1 to 2 weeks on its own before any building work starts. Gas cooker points need a Gas Safe registered engineer, and any new circuits must meet Part P building regulations, both of which are routine but need booking in around the rest of the work. Bespoke or made-to-order cabinetry from a kitchen specialist can also have a 4 to 8 week lead time before it even arrives on site, separate from the fitting time itself.
The single biggest factor in keeping a Cheadle Hulme kitchen fitting on time is deciding on your units, worktop, tiles and appliances before work starts, rather than during. Changing your mind about a worktop material partway through almost always adds weeks, not days, because of ordering and templating lead times.
It's also worth asking your builder or kitchen fitter to walk through the existing pipework, wiring and any walls likely to be affected before you commit to a start date. In older Cheadle Hulme properties this early look can flag issues like outdated electrics or old floor coverings, which are far easier to plan for than to discover halfway through a strip out.
A straightforward refit that keeps the existing layout, units and plumbing positions typically takes 1 to 2 weeks on site. It can take longer if the flooring or electrics need updating as well.
Most homeowners stay in their property, though you'll be without a working kitchen for most of the project. Setting up a temporary kettle, microwave and kitchen area in another room, such as a dining room or utility space, makes this much more manageable.
Unexpected issues behind walls and floors, such as outdated wiring or old solid floors, are the most common cause of delay, along with worktop lead times for quartz or granite. Agreeing your full specification before work starts helps avoid most of these delays.
Based in Stockport. Working across Cheshire and surrounding areas.